The results of an international tender for the provision of turnkey design and construction services (EPCC) of surface facilities for gas fields in the western section of the Bagtyyarlyk contract area have been summed up. The competitive selection was carried out by the Branch of the China National Oil and Gas Corporation "International" in Turkmenistan, China Petroleum Engineering Construction was recognized as the winner.
Within the framework of the project, six fields will be put into operation - Gadyn, North Gadyn, Ildzhik, East Ildzhik, Kishtuvan and West Kishtuvan. In particular, it is planned to build 22 wells, four gas gathering stations, pipelines, utility networks, including electricity and water supply, and other industrial infrastructure. Their total design capacity will be 1.8 billion cubic meters of gas per year.
Note that at present, China Petroleum Engineering Construction is also carrying out the construction of onshore facilities at the West Joramergen, Gokmiyar and Dashrabat fields located in the east of the Bagtyyarlyk contract area.